Journal of Earth Sciences and Geotechnical Engineering

Mystery of Mosul Dam the most Dangerous Dam in the World: Foundation Treatment during Construction

  • Pdf Icon [ Download ]
  • Times downloaded: 10415
  • Abstract

    Mosul dam was constructed on the beds of Fatha Formation (Middle Miocene). The beds of the formation are about 250 m thick composed of Marls, chalky limestone; gypsum, anhydrite, and limestone form a layered sequence. They are highly karstified. As a consequence, plenty of grouting operations were carried out to fill all the cavities, fractures, joints and to stop the seepage under the foundation of the dam. The main grouting operations were Blanket grouting and deep grout curtain. It was necessary to perform an extensive maintenance program to control the seepage process within the grouted zone to stop dissolution of gypsum and protect the safety of the dam.